CASE STUDY

315 Blackness Road

sdb_contracts_dundee

SDB Contracts were contracted to carry out the groundworks on a new turntable garage which would be cut into the existing front garden of the property.

Using a 14t excavator, the SDB Contracts team removed over 700t of material offsite by digging into the existing sandstone landscape. These works had to be perfectly planned and well executed due to being located on a busy road with pedestrians. Once the earthworks were complete, we commenced works on the reinforced concrete slab. 20m3 of concrete was poured and the project was handed over to the builder on programme and on budget.

14t

EXCAVATOR

700t

OF MATERIAL MOVED

20m3

OF CONCRETE POURED